Remove and dispose 4 x 65,000Lt Underground Storage Tanks
Scope of Work
- Excavate and remove overlying hardstand and soil to safely expose and remove UST, fuel pipework and infrastructure
- Demolish and remove existing concrete footings and cathodic protection infrastructure
- Soil sampling and laboratory analysis of UST, fuel infrastructure excavations and temporary stockpiles
- Load and transport UST, fuel pipes and cathodic protection to a certified landfill
- Backfill and compaction of excavated areas using stockpiled and imported material
Equipment Used
- 25 tonne excavator with rock breaker
- 60 tonne franna crane and dogman
- Large posi track
- Truck and dogs
- Prime movers
- Environmental Scientist (SQP)
- Project Manager
- Site Foreman
- Site Labourers
Project Innovations
- Excavated material used to backfill excavation areas to minimise quantity of material imported
- Sourced local suppliers for imported material, crane operations and transport
- Validation sampling and environmental reporting completed in-house
- Certified QHSE management system implemented to ensure staff returned home safely